Thursday, October 31, 2024

Superintendent recommends asking for $21.6 million in local funding

FACT CHECK:  In the article below, Superintendent Thomas Taylor says "none of the key personnel" are still with MCPS.  That is FALSE.  Superintendent Taylor has hired former MCPS Associate Superintendent of Operations back as the MCPS Chief of Staff.  The MCPS Associate Superintendent of Operations is a key person in the Capital Budget process. 

******************************** 



MCPS error leads to $39.3 million state aid shortfall for Woodward High construction

Montgomery County Public Schools (MCPS) is facing a $39.3 million shortfall in funding for the ongoing construction of Charles W. Woodward High School in Rockville due to its state aid calculation errors in 2021, but won’t lose out on state funding in the long run, district staff said Thursday. 

To close the funding gap, MCPS Superintendent Thomas Taylor is recommending to the school board that $17.7 million be reallocated from other district projects and also asking the County Council to provide an additional $21.6 million for the project. 

“I want to make it clear that this issue was entirely MCPS’ fault,” Taylor said at a school board work session on Thursday. “We are working to correct it, and though this will not have a net negative impact on state construction revenues over the long run, it does have an impact on these projects and I’m sorry for that.” ...

...At Thursday’s work session, Taylor said “none of the key personnel” involved in the erroneous submission to the state are still working for MCPS... 

MCPS error leads to $39.3 million state aid shortfall for Woodward High construction

Wednesday, October 30, 2024

WUSA9: Montgomery Co. Public Schools loses out on $39M in funding due to a submission error

The multi-million-dollar loss was due to an error in the Montgomery County Public Schools submission for aid in the Charles W. Woodward Project.

MONTGOMERY COUNTY, Md. — Montgomery County Public Schools has lost more than $39 million in funding due to a submission error, according to a letter from Superintendent Dr. Thomas Taylor.

The 288-page letter outlines a recommended capital budget for Fiscal Year 2026 and includes suggestions on how the district can make up for the huge loss in state aid...

...Janis Sartucci, a member of Parents’ Coalition of Montgomery County wants to know how an almost 40-million-dollar mistake slipped through the cracks.

“There are multiple steps and lots of people involved in approving these construction contracts. This isn’t just someone making a minor error. And, who suffers? The community, schools, this 17 million could be going to other needs in our system.” Sartucci, said...


MCPS loses out on $39M in funding due to a submission error | wusa9.com

Friday, October 25, 2024

@mcps Chief of Staff Essie McGuire Approved a Woodward HS Contract using Non-Prevailing Wages in 2021

 

In 2021, Essie McGuire was the MCPS Associate Superintendent of Operations.  In that capacity she reviewed the Award of Contract for the Project Site Work at the Woodward High School site.  

The Resolution submitted to the Montgomery County Board of Education was brief, but clearly stated that the "project was bid to include both prevailing and non-prevailing wages." 

Using non-prevailing wages means the contracts would not be complying with Maryland procurement law.  

Woodward High School's project was attempting to use Maryland's Built to Learn (BTL) funding.  The BTL funding information sheet makes clear that complying with Maryland's prevailing wage law is required. 


EM
approved this Resolution for presentation to the Board of Education.  In 2021, EM was Essie McGuire, MCPS Associate Superintendent for Operations.

Today, Essie McGuire has been hired back by Superintendent Thomas Taylor to work as MCPS' current Chief of Staff.